Project Summary

View our related links below to read on.

Corporate Overview

Home Project Summary - Ecovillage

Landmatters Currumbin Valley
EcoVillage at Currumbin                  

 

Client

Landmatters Currumbin Valley

Location

639 Currumbin Creek Road, Currumbin Valley, Qld

Contractual Completion Date

February 2008

Original Contract Value

$6.8m

The Ecovillage at Currumbin is a mutli-award wining, sustainable rural-residential development in the Gold Coast hinterland. Landmatters Currumbin Valley was awarded the FIABCI Prix d’Excellence in 2008 for the Worlds Best Environmental Development.

McIlwain Civil completed Stages 3 & 4 of the development for which they were awarded the 2007 CCF Earth Awards Category 2. Upon the successful completion of stages 3 & 4 McIlwain Civil were engaged by Landmatters to complete stages 5 & 6 and the link road which commenced construction in August 2007

Through the initial pre-construction period the collaborative team including McIlwain Civil, Landmatters, the Project Manager (Colin Bear), the Principal Consultant (Bligh Tanner) and the Superintendent, Tim Capes Management Services (TCMS)- via the Superintendent’s Representative, Jason Adams, developed a set of agreed principles and objectives by which the project would abide.

The project contained specific technical areas and sensitive environmental issues which were addressed in accordance with all relevant legislative requirements, contract specifications and MCE internal systems.

The project specifications and guidelines incorporated multiple dams and ponds, stormwater drainage infrastructure, a common services trench, minimised clearing with vehicular and construction traffic excluded from all lots. Specialised construction techniques were adopted to assist in the delivery of the project including laser guided directional boring for the sewer pipeline.

Inclement weather conditions made the completion of Stage 3 & 4 difficult causing significant changes to design and multiple stoppages and delays in the program. The collaborative approach to the project delivery ensured that these stages were delivered on time despite in excess of 2metres of rain falling throughout the duration of the contract.

 

  • 99 Lot Residential Subdivision
  • Construction of a Temporary access across Currumbin Creek
  • 40,000m3 Earthworks
  • 20,000m2 Asphalt Pavements (grades up to 20%)
  • Construction of 13 Ponds and Dams for stormwater detention and visual amenity
  • 2,500m Recycled Water Reticulation
  • 2500m MDPE Gravity and Pressure Sewers
  • 180m Directional Boring (on grade) for Sewer
  • Sewer Pump Station
  • Construction of 26 Stormwater Culvert Crossing (up to 4/3600x2400 RCBC)
  • 5,500m Common Services Trenching (Electrical, Gas, Recycled water, Telstra, Coms)
  • Construction of Main access to the development form Currumbin Creek Road
  • Construction of 150KL of Recycled Water Storage  

       